|
|
|
Activity / Estimate Type |
Conceptual |
Preliminary |
Detailed |
Definitive |
|
Purpose |
Ranking/Rejection |
Economic Feasibility |
Project Approval |
Project Control |
|
Basis of Estimate |
||||
|
Site |
||||
|
Location |
Assumed |
Preliminary |
Optimised |
Final |
|
Geotechnical |
Assumed |
Preliminary |
Final |
Final |
|
Process |
||||
|
Plant Capacity |
Assumed |
Preliminary |
Final |
Final |
|
Process Testwork |
If available |
Advanced |
Complete |
Complete |
|
Energy & Material Balance |
Assumed |
Advanced |
Optimised |
Frozen |
|
Process Flow Diagram |
Assumed |
Decided |
Optimised |
Frozen |
|
Equipment List |
Assumed |
Preliminary |
Optimised |
Final |
|
Design |
||||
|
Status of Design |
Conceptual |
Probable |
Actual |
Actual |
|
Equipment Selection |
Assumed |
Preliminary |
Optimised |
Final |
|
General Arrangement |
||||
|
- Mechanical / Layout |
None / Basic |
Minimal |
Fair Detail |
Complete |
|
- Structural |
None |
Outline |
Fair Detail |
Complete |
|
Piping Drawings |
None |
Basic Layout |
Some Detail |
Advanced |
|
Electrical Drawings |
None |
Single Line |
Some Detail |
Advanced |
|
Detail Design Drawings |
None |
None |
Some |
Advanced |
|
Specifications |
None |
Standard |
Preliminary |
Contract Status |
|
Project Delivery |
||||
|
Procurement Plan |
None |
Preliminary |
Final |
Frozen |
|
Program |
Simple Bar Chart |
Bar Chart with Critical Path |
Critical Path Network |
Critical Path Network |
|
Cost Estimate Method |
||||
|
General Approach |
Data Base Rates |
Single Quote |
Multiple Quotes |
Contract Value |
|
Civil Work |
Sketch Quantities |
Basic Drawing Quantities |
Detailed Take-Off |
Contract Value |
|
Structural |
Sketch Quantities |
Basic Drawing Quantities |
Detailed Take-Off |
Contract Value |
|
Major Equipment Costs |
Data Base |
Single Quote |
Multiple Quote |
Contract Value |
|
Mechanical Work |
% of Equip |
% of Equip |
Manhrs/Tonne |
Contract negotiations |
|
Piping Work |
Rough Quantities |
Prelim. Take-off |
Take-off |
Detailed Take-Off |
|
Instrumentation |
% of Equipment |
% of Equipment |
Take-Off |
Detailed Take-Off |
|
Electrical Work |
$ per kW |
$ per kW |
Take-Off |
Detailed Take-Off |
|
Indirect Costs |
% of Total |
% of Total |
Calculated |
Calculated |
|
Economic Analysis (DCF) |
Not Meaningful |
Reliable Results |
Final Decision Tool |
n/a |
|
Contingency for Undefined Items |
Up to 30% |
15% - 25% |
10% - 15% |
5% - 10% |
|
Typical Accuracy |
± 25% to 30% |
± 15% to 25% |
± 10% to 15% |
± 7% to 10% |
- MS Excel format - Estimate
- Lotus 123 wk4 format - Estimate (a self executing zip file)
- Lotus 123 wk4 format - Estimate (a classic zip file)